The Construction of Road L1756 using Labour Intensive Construction

  • Test
  • 5
  • The Construction of Road L1756 using Labour Intensive Construction
Description
OVERVIEW
Project Details
ABOUT THE PROJECT
Gallery
SEE OUR TEAMS
This labour intensive pilot project entailed the construction of an all weather access road to the Mzimba Primary School, the Emzamweni High School and the community alongside the road. 4 Emerging contractors were used to lay 3540m² of concrete paving blocks.

CLIENT: Kwazulu Natal Department Of Transport

VALUE: R1.7 Million

KEY FEATURES

  • Road surface area: 3 540 m²
  • Cement bricks laid: 113 122
  • Earthworks excavated manually: 396 m³
  • Concrete edge restraints: 56 m³
  • Schools affected by the road: 2
  • Homestead access improved by the road: 53

 

AWARDS
2013 SAICE AWARDS: Community Based Construction – Winner

JOBS CREATED: 29

PROJECT OUTPUT: 0.6km of Block Paved Concrete Roads (3540m²)

2010 – 2011 (4 Months)